ZeonChemicals_ProjectTracker.pbix — Power BI Desktop
Overview
Skid Progress
Issues Log
Week 38 · Sep 2024
Avg. Completion
14%
Across all skids
Active Phase
Fabrication
Piping + Structure
Skids Tracked
3
AB · HPO · KOH
Tasks Pending
6
of 8 categories
AB Skid
13%
Overall
Fab – Piping2%
Fab – Structure48%
Galvanizing32%
FAT0%
Shipment0%
HPO Skid
13%
Overall
Fab – Piping2%
Fab – Structure48%
Galvanizing32%
FAT0%
Shipment0%
KOH Skid
16%
Overall
Fab – Piping40%
Fab – Structure48%
Galvanizing20%
FAT0%
Shipment0%
Connected to workspace
Zeon Chemicals · RO230109-SS01