ZeonChemicals_ProjectTracker.pbix — Power BI Desktop
Overview
Skid Progress
Issues Log
Week 38 · Sep 2024
Avg. Completion
14%
Across all skids
Active Phase
Fabrication
Piping + Structure
Skids Tracked
3
AB · HPO · KOH
Tasks Pending
6
of 8 categories
AB Skid
13%
Overall
Fab – Piping
2%
Fab – Structure
48%
Galvanizing
32%
FAT
0%
Shipment
0%
HPO Skid
13%
Overall
Fab – Piping
2%
Fab – Structure
48%
Galvanizing
32%
FAT
0%
Shipment
0%
KOH Skid
16%
Overall
Fab – Piping
40%
Fab – Structure
48%
Galvanizing
20%
FAT
0%
Shipment
0%
Connected to workspace
Zeon Chemicals · RO230109-SS01